Facility Updates

Work is now underway at Toronto Rehab to build iDAPT, one of the world's most advanced and unique rehabilitation research facilities.

While many facilities are now being developed, significant construction of iDAPT will coincide with the redevelopment of Toronto Rehab's University Centre. By the end of the decade, all iDAPT facilities, including the centrepiece Challenging Environment Assessment Lab (CEAL) will be fully operational.

iDAPT Facilities

Current Status

Date of Completion

Fund
CEAL Lab and pallet preparation area To be located in redeveloped University Centre
 
January 2009 CFI

Intelligent Environment Laboratory

Renovations on 4th floor of U of T Rehab Sciences Building completed
 

May 2003
 

CFI

Physical Function Laboratory

Operational in basement of U of T Rehab Sciences Building
 

May 2003
 

CFI

Rehabilitation Engineering Laboratory

Renovations complete at Lyndhurst Centre
 

July 2006
 

RHF

Electronics Workshop

 

To be located in redeveloped University Centre
 

February 2011

RHF

Expanded Mechanical Workshop
 

To be located in redeveloped University Centre

February 2011

RHF

Rapid Prototyping Workshop

Ttemporary rented space at 180 Elm St (in use until new hospital building opens in January 2011
 

June 2006/ February 2011

CFI

Research and Design Studio
 

To be located in redeveloped University Centre

February 2011

RHF

Communicative Function Laboratory

Renovations of the lab space completed
 

May 2003

CFI

Cardiopulmonary Laboratory 

Construction started in renovated space on 12th floor of University Centre
 

July 2006

RHF

Researcher Workstation and Teamwork Spaces

Phase 1 - Renovations for 66 workstations and 28 teamwork spaces ongoing (11th floor and part of 12th floor)

Phase 2 - New construction of workstations and teamwork spaces to be part of redeveloped University Centre

Phase 3 - Renovations for 14 workstations and 1 teamwork/ meeting/interview room, 1 interview room and 1 observation area to be part of redeveloped University Centre
 

July 2006




February 2011




February 2011

RHF

Stakeholder Rooms

 

Renovations underway at University Centre

July 2006

CFI

Swallowing/Rehabilitation Research Laboratory

Construction started in renovated space on 12th floor of University Centre
 

July 2006

RHF

Biomechanical and Physiological Data Analysis Laboratory
 

To be located in redeveloped University Centre
 

February 2011

RHF

Home Environment Lab
 

To be located in redeveloped University Centre

February 2011

RHF

Falls Laboratory

 

To be located in redeveloped University Centre
 

February 2011

RHF

Institutional Environment Lab

To be located in redeveloped University Centre
 

February 2011

RHF

Instrumental Development Laboratory

To be located in redeveloped University Centre
 

February 2011

RHF

Secure Data Analysis Centre

To be located in redeveloped University Centre
 

February 2011

RHF

Sleep Laboratory

 

To be located in redeveloped University Centre
 

February 2011

RHF

Movement Evaluation Laboratory

Renovation will not start until redevelopment of University Centre nears completion
 

February 2011

RHF

 

 