Project Timeline
|
|
1
|
Nov.-Dec.
2002 |
Existing parkette to be replaced
with parking spaces, to offset loss of spaces in main
lot. At City's request, there will be no entrance to these
spaces from Dunn Ave. |
|
2
|
Nov. - Dec.
2002 |
Driveway to loading dock
will also become entrance to new staff parking lot. City
is opening Close Ave. to two-way traffic between Springhurst
Ave. and the driveway. |
|
3
|
Dec. 2002 |
Two houses owned by the hospital
will be put up for sale, to raise funds for upgrading
of other houses owned by the hospital. |
|
4
|
Dec.
2002 -
Jan. 2003 |
New, fenced playground
for toddlers and pre-schoolers attending Sunflower House
to be located south of the centre. Temporary for duration
of construction. |
|
5
|
Dec.
2002 -
Jan. 2003 |
Driveway becomes
the only entrance and exit to main parking lot during
construction. Will become an exit only when construction
is completed. |
|
6
|
Dec.
2002 -
Jan. 2003 |
Existing driveway
to main parking lot will become child drop-off and pick-up
zone (no tokens needed). No more access to main parking
lot from driveway. |
|
7
|
Dec.
2002 -
Jan. 2003 |
A new driveway
for construction vehicles will become entrance to the
main parking lot when construction is completed. |
|
8
|
Dec.
2002 -
Jan. 2003 |
Hoarding (safety
wall) erected around construction site, and construction
begins. |
|
9
|
Jan.
2003 |
During construction,
school employees and hospital students will not be permitted
to park in hospital lots, to ensure that spaces are available
for hospital staff and visitors. |
|
10
|
Spring
2003 |
New, landscaped
area to be put in by hospital for public use. |
|
11
|
Spring
2004 |
New parking spaces
with designated area for child drop-off and pick-up, and
a new playground for pre-schoolers that is 20% larger
than the current playground. |
|
12
|
Spring
2004 |
New walkway for