Please note that dates are subject to change
Date |
Milestone |
| November 2005 | First community information meeting on University Centre redevelopment |
| April 13, 2006 | Government announces approval of University Centre redevelopment and expansion through ReNew Ontario. |
| July 2007 | Government approval of the Early Works phase of the project. Early Works includes: staff relocations, internal renovations to accommodate patient care and demolition of south tower |
| August 2007 | Relocation of non-patient care services off-site to help make room for patient services to be moved from south wing in preparation for demolition Official announcement by Minister of Health and Long-Term Care of the names of prequalified construction companies released |
| October 2007 | Release of RFP for reconstruction/renovation project |
| November 2007 - February 2008 | Site preparation begins, consisting of renovations to existing east wing to prepare more space for services vacating the south tower |
| January 29, 2008 | Second community information meeting |
| February-March 2008 | Site preparation work on east wing completed. Services relocate from south tower to east wing. |
| March – July 2008 | Site preparation continues with demolition of south tower RFP/Tender approved. Winning bidder announced. |
| Summer 2008 | Construction of 13-storey patient care south tower begins. |
| 2010 | Renovation of existing east wing and north wing begins |
| Late 2011 | Project completed |